Hi,
Actually, one can get a number of test items in the project plan via Project.TestItems.ItemCount property. Then one can iterate over project plan, count the number of enabled test items (see code example in the help topic for the Project.TestItems.ItemCount property), convert to percentage and visualize the result via Indicator object as it was suggested by MW_Didata.
The case here (if nothing changed during past several years since the time when I implemented something similar) was that groups in project plan look pretty much as test items and it is not that easy to distinguish group from actual test item. And this resulted in somewhat 'strange and visually unclear' behavior of the tests run progress displayed by the Indicator object.