SUITE events

I don't think there is, but is there a way to define events on suite start and stop?



S
  • irina_lukina's avatar
    irina_lukina
    Super Contributor

    Hi Stephanie,


    As far as I know, there are no special events occurring on the project suite's start and stop. However, TestComplete provides you with the OnStartTest and OnStopTest events that occur every time the test run starts or stops.


    For more information on TestComplete events, refer to the List of TestComplete Events help topic.


    I hope this information helps :)

  • sastowe's avatar
    sastowe
    Super Contributor
    Oh that clarifies a pretty simple concept for me that I was fuzzy on. A test "run" is one instance no matter how you start it, from suite, from project or from run this procedure in the editor. I had a bit of a mind block about that. Thanks. That is what I need.