I run test complete 12.6.
Say I have a project with 4 test suites & I start executing all of them.
Suite#1 has 15 tests.
Say test Item 3 fails, how do I stop the execution of the rest of 12 tests if number 3 fails ? then continue with Suite#2,3,4
Thank you
Hi
Need to uncheck "Stop on error" option in the project's settings
select "Project" item in "Stop on error" combobox for all tests
uncheck "Stop on error" option in the suite's settings
Hi
Need to uncheck "Stop on error" option in the project's settings
select "Project" item in "Stop on error" combobox for all tests
uncheck "Stop on error" option in the suite's settings
Thank you :) How do you get to the last screenshot ?
Also, If I need to leave few test items out - Can I keep the test item under Stop On Error ?
1. Need to click on Project Suite
and select "Test Items" tab
2. If you select "Test Item" item in "Stop on error", other Test items in project will be executed.