I am working within a team that is testing an administration system. We are working in two project suites because working in the same project was slowing the recording down and continually asking to update.



To bring all the tests together I add an "existing item" from the other project suite. When I try to run these tests they immediately fail because ojects cannot be found or do not exist. If i then re-point the test actions they run perfectly, obviously this is very time consuming and impractical.



It seems that when the test is brought over the name mapping does not come with it and the test is struggling to find the objects because they are not mapped in my suite. Is there a way of merging the name mapping from the 2 project suites so that all tests will run in either suite.