AR
13 years agoOccasional Contributor
Issue faced while linking items
Additional care is needed in ALM, wherever you "Link to Items...".
Following scenario explains the issue:
1. Initially link one item to another item. (e.g., Link Task0 to Task5.)
2. Save the work
3. Open a second item and try to add a link (e.g., Link Task1 to Task6).
4. Now the issue noted here is that, ALM remembers the initial link to Task5 and by default will have Task5 checked
5. Each and every time, whenever we try to link the items, we need to verify that only the items we want linked are checked.
Is that the behaviour expected? When we try linking more than 50 items, it is real hard for us to verify the linkage.
Attached video demos the issue