Forum Discussion
thomas_brossama_1
11 years agoContributor
Hi,
I have tried to remove the SynchPoint (ref SPC here) from my master project. Unfortunately this does not work.
I managed to reach for both tests the same Sync point. But it hangs and wait afterwards(Glasshour icon displaying "synchronizing")
How to pass the synchronization point for both tests in order to continue the execution? What blocks the execution?
Thank you
I have tried to remove the SynchPoint (ref SPC here) from my master project. Unfortunately this does not work.
I managed to reach for both tests the same Sync point. But it hangs and wait afterwards(Glasshour icon displaying "synchronizing")
How to pass the synchronization point for both tests in order to continue the execution? What blocks the execution?
Thank you
Related Content
- 5 years ago
- 5 years ago
- 10 months ago
Recent Discussions
- 8 hours ago