How to run more than 1 project suite with test execute
Hi there
Please could someone advise me.
If i have more than 1 project set up in Test Complete and both projects have keyword tests to run,how would i go about setting this up under the execetion plan so that test executes picks it up and runs all test cases under both projects. Currently my test script is set up like this and only picks up the 1 project and tests under the execution plan.Can this be done?
C:\Program Files (x86)\SmartBear\TestExecute 15\x64\Bin\TestExecute.exe" "C:\Users\Tina\OneDrive - DATASCOPE\Test Complete\WHClient\WHClient.pjs" /run /exit /Project:"Project_WH Client"