Forum Discussion
Do you really need to execute the projects simultaneous? Or one at a time in queue?
If you just need to queue it I have created a simple batch file to assist me running the projects:
something like this:
"runner.bat"
:repeat
@echo off
setlocal enableextensions enabledelayedexpansion
set "CAMINHOBASE=C:\tests"
SET "run_PROJECT1=1"
SET "run_PROJECT2=1"
SET "run_PROJECT2=0"
:: value = 0, doesn not run, 1 runs
:: PROJECT1
set "NOMEPROJETO=PROJECT1"
IF !run_PROJECT1!==1 (
set "CAMINHOPROJETO=%CAMINHOBASE%\%NOMEPROJETO%\%NOMEPROJETO%.mds"
"C:\Program Files (x86)\SmartBear\TestComplete 10\Bin\TestComplete.exe" "!CAMINHOPROJETO!" /run /project:"%NOMEPROJETO%" /exit /SilentMode
)
:: PROJECT2
set "NOMEPROJETO=PROJECT2"
IF !run_PROJECT2!==1 (
set "CAMINHOPROJETO=%CAMINHOBASE%\%NOMEPROJETO%\%NOMEPROJETO%.mds"
"C:\Program Files (x86)\SmartBear\TestComplete 10\Bin\TestComplete.exe" "!CAMINHOPROJETO!" /run /project:"%NOMEPROJETO%" /exit /SilentMode
)
endlocal
goto repeat