QA Complete and Test Complete Integration
Hi,
I have two queries on QA Complete and Test Complete Integration
Query1: I installed the required Agent for Bridging Connection between QA Complete and Test Complete(Agent20.exe). I was able to zip up the project suite and Add it to one of Test cases I created under Test Library in QA Complete. The run went fine with Test complete getting invoked, running the test and closing it. Now if i have 10 keyword test cases under my project suite its still mapped to single test case in QA Complete. Is there a way by which we can create multiple Test cases and link it one suite under QA Complete.
Query2. We have a hybrid framework using VB scripting that we have customized on Test Complete. Now the test run happens in batch and the results are updated in an Excel Report. Is there a way by which we can tell the code to directly update the results in QA Complete for that particular testcase. Like we have in QTP->ALM
Awaiting Support