Hi,
We search if we can configure a load test and stress test in loadNinja tool.
For example, for the load testing we will search to run this similar configuration following. But we didn’t see how to configure this type of configuration in LoadNinja tool:
Load configuration : { target-VU: 35, duration: "1m" }, // Ramp-up of 0 to 35 Vus on 1 minute
Thresholds : Metric: Response Time Statistic & condition: >= 99 % Value: 500 ms |
If we try to simulate the same configuration in your tool we can’t have the same diagram:
|
Thank you in advance for your answer,
Regards,
Y.K
LoadNinja only provides the option to stop the test abruptly or to let the test run until all virtual users have completed their sessions. There is no built-in functionality to gradually decrease the number of virtual users during the test.
As of now, you can only achieve something like 30-33 minutes of your graph: