John_D
9 months agoContributor
there are some configuration based things, but in general a user will 'send to complete' if no defects are present, or send to rework if there are defects.
- brianswilson9 months agoNew Contributor
Thank you for your response John. The instructions I quoted must be badly worded. They tell the user to somehow "Indicate" they have completed their task then the review will move to the next phase once all required participants have checked in. This makes it sound like the action of moving to the next phase is different from indicating the participant is done.
I'd suggest that this instruction be made a little less vague concerning how to "indicate" completion and when the phase transition occurs.