Forum Discussion
jfelix
4 years agoSmartBear Alumni (Retired)
Hi, testcaseone! Thanks for your question.
Test cycles are designed to be used within a sprint. Then, you can update their status as you perform those tests.
If you have a test execution that is not linked to any test cycle (for example, you executed a test case directly from a Jira issue), you can't add those results to a cycle.
If you use automation tools to perform the tests, you can import the result file into Zephyr Scale: it'll create a test cycle with the test cases, along with their status.
I hope this answers your question, but if this solution does not meet your needs, you may raise a feature request in the Ideas Portal:
Cheers!