Hello, we need to move test executions between test cycles in our zephyr scale. I don't see an option to do that. when i move it it creates a new test execution instead. Help please, newbie to zephyr here. Thank you
Labels:
- Labels:
-
Academy
1 REPLY 1
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
05-22-2023
02:36 AM
05-22-2023
02:36 AM
Hey @jbelgica
Post your query in the Zephyr Scale community here
https://community.smartbear.com/t5/Zephyr-Scale/ct-p/zephyr-scale-community
This is the Zephyr Enterprise community which is a different standalone offering outside of Jira
Hope you find your answers there 🙂