Is there a way to set up an execution plan starting with a browser loop, then keyword tests as child test items under the browser loop?    I have multiple tests that I want to cycle through 3 browsers but I want them to run in one browser at a time.   

Thanks for the help.

1 REPLY 1
vinniew
Staff

Hi @lnivy28 

 

I dont think there is a specific operation for this as the browser loop is specific to the keyword test rather than the group of tests in the execution plan. 

 

However there are some considerations and workarounds.

1)

If you have Cross Browser Testing, you could run the same test across multiple browser configurations from TestComplete all at the same time. 

 

https://support.smartbear.com/testcomplete/docs/app-testing/web/cross-platform/index.html

 

As you can see this can be managed in the execution plan 

 

https://support.smartbear.com/testcomplete/docs/app-testing/web/cross-platform/run-parallel.html

 

2)

If this doesnt work, you could simply parameterize the test and call that browser in the execution plan

This may be more in line with what you want to achieve. 

 

See the property section here

https://support.smartbear.com/testcomplete/docs/working-with/managing-projects/execution-plan/proper... 

 

Hope the above helps! 

 

KR

Vincent 