mperron1
4 years agoOccasional Contributor
Move an Execution to a Cycle
Users have created executions ad hoc from the traceable issues instead of in a cycle. I cannot figure out how to move the execution into the cycle so we can appropriately report/track progress. There are too many notes and attachments to make manually moving everything reasonable.
Hi mperron1,
Unfortunately, it is not possible to move ad hoc executions to test cycles. Perhaps you can try out the API and see if there's any way of automating this copy/paste if you have a large number of executions?
https://support.smartbear.com/zephyr-scale-server/api-docs/v1/
However, I can't see an endpoint that would be particularly helpful for you...