Bob_C
1 year agoContributor
Burn Down Charts
I have a project that was recently completed, and tried to look at a Burn Down Chart for it. I have 3 test plans P1, P2, P3 and these cover all of the test cases. If I create a dashboard gadget for...
Seems similar to the issue I'm seeing, all test cases (bar one which was deferred) have been completed, yet the Burndown shows this:
Says I still have 29 remaining to be executed! This was the criteria I put in:
Showing 100% done