Re: Burn Down Chart Dashboard gadget does not display accurate burn down
I have submitted several tickets in the past regarding problems with the Agile Burndown Chart not reflecting the work remaining in the sprint (eg.GHS-9079andGHS-6788). There should at least be an option so that value on the (red) burndown line will balance to the sum total of the "Remaining Estimate" on each ticket in the sprint. Subtracting the time logged from original estimate may have some value but it certainly does not give an understanding if the work can be completed in time for a pending release date or how much time will be carried forward to a following sprint. Remaining estimates are often increased once work has started and you do not want to also increase the Original Estimate otherwise you cannot provide guidance on estimate accuracy for future sprints. funko pop danmark1.6KViews1like0Comments