Zephyr Cloud Test Execution Order

Within test cycles, for a project, we are trying to set an execution order for the tests. I am able to reorder test cycles but I am not able to rearrange the order of the individual tests within the cycle.  I read some posts last year asking the same thing but I never saw a response of if this was made available to complete within the software.

1 REPLY 1
ebarbera
Staff

Hi @Jbarnes1359 -

 

What method are you using to execute these tests?

 

This document may help get  you started: https://support.smartbear.com/zephyr-squad-cloud/docs/tests/organize.html

 