What is the best way in Load Ninja to create heavy load
SOLVED- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-24-2022
07:14 AM
11-24-2022
07:14 AM
What is the best way in Load Ninja to create heavy load
I would like to create multiple scenarios to generate heavy load on the system but Load Ninja -Load configuration --duration of test greyed out -- and can go max 7 minutes . So what is the best one to do heavy load duration based or iteration based ?
Solved! Go to Solution.
1 REPLY 1
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-24-2022
07:25 AM
11-24-2022
07:25 AM
Hi Shafiqa,
"Duration of Test" is the summary of "Peak time" and "Ramp-up time". So in case, you would like to increase the "Duration of Test" you can increase the "Peak time" of the load test.
Both Duration and Iteration-based load tests can generate the heavy load test, it depends on what kind of approach you want to take. You can find more details about the configuration in our documentation - Link.
Greetings,
Tom.
LoadNinja Customer Care