Forum Discussion

Lasertop's avatar
Lasertop
Occasional Contributor
2 years ago

Is there an easy way to move a group of test cases from one project to another?

So I have about 300 test cases for Project A and the company has now decided to create Project B which has most of the same requirements and there fore needs most of the existing 300 test cases.  How does one go about copying those test cases from Project A in Zephyr to Project B?

  • MisterB's avatar
    MisterB
    Champion Level 3

    You can use the export feature to export from project A to project B (select all test cases > export > etc.) and then import into project B.  That's really it and would take about 5 minutes to perform.

     

    Or, if keeping Project A test cases in Project A is OK, then you could leave them where they are, and add them to test cycles in Project B: go to the test cases tab, click the add button and then change the project that it's pointing to...