How to use +days option to avoid an specific day.
Hi all, I have some tests that I need to execute almost everyday, tests always make a search 3 days in the future. The problem is that I always have to change the date manually to 3 days in ...
- 10 years ago
Hi,
Thanks for your answer. Yesterday we could find the solution for my problem, I will explain because it could be useful for other people:
Command: ${=import java.text.SimpleDateFormat; new SimpleDateFormat('yyyy-MM-dd').format(new Date() + 31*5 + (int)(Math.random()*10))}
This exemple uses current day + 31*5 + random value between 0 and 9
In the file attached you can see where the code were pasted. This window was opened with double-click in the project.