Forum Discussion

Chen-CPA's avatar
Chen-CPA
New Contributor
5 years ago

Very slow when switch between test steps in ReadyAPI after convert to composite project

  We have just started with ReadyAPI and added only 4 sample requests/steps in a new project. It work well at the beginning, but when I tried to convert it to the composite project and integration w...
  • richie's avatar
    richie
    5 years ago

    Hey Chen-CPA,

    If your resourcing isnt a problem then i think id convert my composite file back to flat .xml then back again.

    Id be curious if the behaviour disappears and then appears over time again.

    Other option is that depending on the above test, i might submit a support ticket to smartbear

    Rich