Forum Discussion
barbarae
14 years agoStaff
Hello Sergio,
The color coding is based on the Finish Date - not status - so you can easily see if you are behind on follow up on a Defect (or any other item)
If the Estimated Finish Date is today, the item is green.
If the Estimated Finish Date is in the past, and percent complete is not 100, the item is red.
Everything else is plain black text.
Hope that helps!
The color coding is based on the Finish Date - not status - so you can easily see if you are behind on follow up on a Defect (or any other item)
If the Estimated Finish Date is today, the item is green.
If the Estimated Finish Date is in the past, and percent complete is not 100, the item is red.
Everything else is plain black text.
Hope that helps!
Related Content
- 5 years ago
- 2 years ago
Recent Discussions
- 12 days ago