Forum Discussion

hjames7796's avatar
14 years ago

Project Plan - Percent Complete

On the Project Plan tab, there is a percent complete column.  This column can be manually updated with the percent complete.  However, when the project plan is imported into MS Project, the percentages that were entered manually and not calculated by adding hours do not show in the %Complete column.  Is that data fed into a different column within MS Project?  Please see the attached screen shots for an example.
  • Hi Heather,

    MS Project actually calculates that field based on estimates and actuals -  so if you've made an override in ALMComplete - MS Project knows nothing about it.

    Thanks for the question!