Forum Discussion
vinniew
Staff
You can configure this in the project items/Execution plan.
This is where your test items/groups/sub groups reside.
You can individually apply different time outs and on error controls, such as continuing, stopping the item, stopping the whole test etc
https://support.smartbear.com/testcomplete/docs/testing-with/running/control-test-flow/overview.html
Check it out using the above link
KR
Vinnie
SangeetNenwani
3 years agoContributor
Hello vinniew