Test Case Status in Requirements view

SOLVED
Occasional Contributor

Test Case Status in Requirements view

When does the Test case status get updated in the requirements list?

I have created a requirement for the project and linked it to a specific Test case, and marked it as 'In Scope'.

When I sibsequently run the test case and the status is 'Finished', the test case on the Requirements tab still shows [- not run -]

I expected it to be set to [FINISHED], as shown on the linked page.

 

http://readyapi.smartbear.com/_detail/structure/projects/window/requirements/main.png?id=features%3A...

 

requirementsTestStatus.jpg

1 ACCEPTED SOLUTION

Accepted Solutions
Occasional Contributor

Re: Test Case Status in Requirements view

I have discussed this with Smartbear via their support desk - any test cases that are run from with the test case linked to the requirement MUST have the option 'Run primary TestCase (fail if already running)' set for the requirement setting 'FINISHED' or 'FAILED' etc to be updated approriately.

I have attached a screenshot of the option to demo.

5 REPLIES 5
Community Manager

Re: Test Case Status in Requirements view

Hi Anneparr,

 

Are you using the latest Ready! API version? Please make sure that you see the same behavior in our latest maintenance built. You can download it here:

https://support.smartbear.com/downloads/readyapi/nightly-builds/

 

 

---------
Tanya Gorbunova
SmartBear Community Manager

Did my reply answer your question? Give Kudos or Accept it as a Solution to help others.↓↓↓↓↓
Occasional Contributor

Re: Test Case Status in Requirements view

I will try this if I can - but currently I cannot use 1.5.0, only 1.4.1, as when I try to use 1.5.0, my Ready!API license won't work - I am told that 'too many copies have been activated' . I have raised a support issue for this

Contributor

Re: Test Case Status in Requirements view

I had the same issue, I had to send out emails/ open support ticket and lost a week on this. Smartbear has to fix this problem.

Occasional Contributor

Re: Test Case Status in Requirements view

I have discussed this with Smartbear via their support desk - any test cases that are run from with the test case linked to the requirement MUST have the option 'Run primary TestCase (fail if already running)' set for the requirement setting 'FINISHED' or 'FAILED' etc to be updated approriately.

I have attached a screenshot of the option to demo.

Community Manager

Re: Test Case Status in Requirements view

Hi Anneparr,

 

Thanks for sharing the solution with us!

 

---------
Tanya Gorbunova
SmartBear Community Manager

Did my reply answer your question? Give Kudos or Accept it as a Solution to help others.↓↓↓↓↓
New Here?
Join us and watch the welcome video:
Watch the new Interview
Top Kudoed Authors