Forum Discussion
nmrao
Champion Level 3
Can you elaborate what you mean?
livevox084
7 years agoOccasional Contributor
Hi Rao,
Sorry for delayed replay.
I was busy with some urgent work.
I tried your example suite.
It has solved little bit but not everything.
In your project "runSuites" step runs disabled the sequential and parallel test suites.
And this project is not waiting until these these sequential and parallel test suites complete.
Which i mean it shows Project level status Finished before the Test Suites finish.
Look at my screenshot:
But definitely it is better than my design because it completing the project atleast.
I appreciate your help.
Thanks,
Rajendra Prasad
- nmrao7 years agoChampion Level 3I provided a sample project which was readily available with me and gave it to you thinking it might help and you can apply it for your case, not given you as a complete solution. Glad it has helped.
If you can provide the changed project of your, then I can take look see if I help to improve if possible.
Related Content